Scope of Works – Example (NDIS Bathroom Modification)
A Scope of Works (SOW) outlines the full details of an NDIS bathroom modification, including tasks, materials, installation methods, safety requirements, and compliance notes. This example demonstrates how NSW Trading Pty Ltd prepares clear, professional, NDIS‑aligned documentation for approval.
Project Overview
Participant: [Name] Address: [Suburb, NSW] OT: [Occupational Therapist Name] Modification Type: Complex Bathroom Modification Purpose: Improve safety, accessibility, and independence for daily showering and toileting tasks. NDIS Category: Home Modifications – Complex (CHM)
Summary of OT Recommendations
The Occupational Therapist has recommended:
Removal of existing shower screen and raised hob
Installation of a hobless (walk‑in) shower
Installation of a fold‑down shower seat
Installation of handheld shower head
Installation of accessible mixer tap
Installation of grab rails at OT‑specified heights
Installation of non‑slip flooring
Installation of accessible toilet
Installation of shower curtain and track
Improved lighting for safety
Repositioning of plumbing fixtures for accessibility
All recommendations are based on functional assessment and safety risks identified by the OT.
Scope of Works – Detailed Breakdown
1. Site Preparation & Demolition
Protect surrounding areas with dust sheets and floor coverings
Remove existing shower screen
Remove raised shower hob
Remove existing floor tiles
Remove wall tiles as required
Remove existing toilet (if applicable)
Remove basin or vanity (if applicable)
Dispose of all waste materials responsibly
2. Plumbing Works
Reposition shower mixer to OT‑recommended height
Install new accessible mixer tap
Install handheld shower head with adjustable rail
Reposition waste outlet for hobless shower
Install new accessible toilet (Caroma Care 800 or OT‑recommended model)
Ensure all plumbing complies with AS 3500
3. Electrical Works
Install new LED downlight(s) for improved visibility
Install 3‑in‑1 heater‑light‑fan unit (if recommended)
Ensure switches are placed at accessible heights
All electrical work completed by licensed electrician
Provide Electrical Certificate of Compliance
4. Carpentry & Wall Reinforcement
Install wall blocking behind shower and toilet areas
Reinforce walls for grab rail installation
Prepare wall framing for hobless shower layout
Ensure all reinforcement complies with AS 1428.1
5. Waterproofing
Apply primer to all wet areas
Apply first waterproofing coat
Apply second waterproofing coat
Install waterproofing membrane to shower area
Provide Waterproofing Certificate
6. Tiling
Install non‑slip floor tiles (wet‑area rated)
Install wall tiles to required height
Ensure smooth transitions for wheelchair access
Grout and seal all tiles
7. Shower Area Installation
Install hobless (walk‑in) shower base
Install fold‑down shower seat at OT‑recommended height
Install handheld shower head
Install shower curtain and track
Install accessible mixer tap
8. Grab Rails Installation
Install grab rails according to OT measurements:
Vertical rail near shower entry
Horizontal rail inside shower
Angled rail near toilet
Additional rails as recommended
All rails installed into reinforced wall blocking.
9. Basin & Tapware Installation
Install wall‑mounted basin
Ensure clear under‑basin wheelchair access
Install lever mixer tap
Install accessible mirror at OT‑recommended height
10. Toilet Installation
Install accessible toilet (Caroma Care 800 or OT‑recommended model)
Install raised toilet seat (if required)
Install toilet support frame (if required)
Install toilet grab rails
11. Finishing Works
Install towel rails, toilet roll holders, and accessories at accessible heights
Seal all joints and edges
Clean bathroom thoroughly
Remove all waste and debris
Compliance Documentation Provided
At completion, NSW Trading Pty Ltd will provide:
Waterproofing Certificate
Electrical Certificate
Plumbing Compliance Certificate
Builder Compliance Notes
Product Information Sheets
Before & After Photos
Warranty Information
All work complies with:
AS 1428.1 – Access & Mobility
AS 3740 – Waterproofing
AS/NZS 3000 – Electrical
AS 3500 – Plumbing
NDIS Home Modification Guidelines
NSW Building Code
Estimated Timeline
Minor Modifications: 1–3 days Full Bathroom Modifications: 7–14 days Complex Structural Modifications: 2–4 weeks
Timeline may vary depending on NDIS approval, product availability, and site conditions.
Frequently Asked Questions
Can this Scope of Works be used for NDIS submissions?
Yes. This example follows NDIS documentation standards.
Do you provide customised SOW documents?
Yes. Every project receives a tailored Scope of Works based on OT recommendations.
Do you work with OTs and Support Coordinators?
Yes. We collaborate closely throughout the entire process.
Do you provide itemised quotes?
Yes. All quotes are detailed and NDIS‑compliant.
Service Areas
Sydney Sutherland Shire St George Canterbury‑Bankstown Inner West Eastern Suburbs Western Sydney South‑West Sydney Surrounding regions
Request a Custom Scope of Works
If you need a detailed Scope of Works for an NDIS bathroom modification, our team is ready to help. We provide fast quotes, clear documentation, and fully compliant installation services.
Contact us today to begin your next home modification project.